Our WBS

 

 

Phase I: March -  May

Design Phase

- Conceptual Design

- Final Design

 

Phase II : June & July

Design Phase

- CAD Drawing

- BOM (Bill of Materials)

 

Phase III : August

Manufacturing Phase

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday

Saturday

1

2
Discussing about the coming schedule

3

Start machining part and prepare the presentation

Lathing + Milling

4

Lathing + Milling

Bend Saw

 

5

Lathing + Milling

Surface Finishing

6

7

8

9

Testing of circuit

Drilling

 

10

Testing of circuit

Drilling

11

Testing of Penumatics System

CNC Folding

12

Surface Finishing: Sand Blasting

Testing of Penumatics System

13

14

15

16

Testing of Penumatics System

Laser Cut

17

Testing of Penumatics System

Heat Bendering

18

Electroplating of most of the parts

Painting

19

Electroplating

 

 

20

21

22

23

Electroplating

Sub-Assembly

24

Sub-Assembly

25

Assembly

26

Video Taking

Preparing for Final Presentation

27

28

29

30

Final Presentation

31

 

 

 

 

Machining Methods of Each Part